Construction
Projects
Apartments
– Proposals have been submitted for a
design/build team. Interviews are scheduled
to be conducted in July to select the team.
Baseball/Softballs
Fields – Proposals have been
submitted and are under review.
David
G. and Jacqueline M. Braithwaite Building, College
of Nursing and Health Sciences –
Building to open by fall semester. The two-story
facility will contain about 37,000 square feet
and house classrooms, a student lounge area,
conference room, study labs, computer labs,
nursing skills labs and faculty offices.
Work
on the David G. and Jacqueline M. Braithwaite
Building progresses during the month of June
Dormitory
– An architect has been selected to design
the building.
Louise
Herrington Patriot Center – Building
to open by fall semester. The 127,500 square-foot
complex will house classrooms, faculty offices,
indoor jogging/walking track, exercise equipment,
free weight area, gymnasium/convocation area
with volleyball and basketball courts, racquetball
courts and an outdoor pool.
Follow
this link to view the LIVE Web Cam at Patriot
Center Construction Site
Parking
Lot – A contract has been awarded
to C Construction to construct a 245-space parking
lot in front of the Cowan Center (facing Varsity
Drive). The parking lot will include sidewalks,
lighting, landscaping and irrigation. Work expected
to be completed in September.
Premier
Soccer Field – Request for Proposals
are being prepared.
Longview
University Center monument signs –
Proposals were opened in June. A contract is
expected to be awarded in mid-July. There will
be two 46-foot lighted concrete and masonry
monument signs, one on each side of the entrance
to the Longview campus.
Palestine
Signs – Request for proposals
are being prepared.

Contact
person: Emily Battle,
(903) 565-5604

|