Apartments – Proposals have been submitted for a design/build team. Interviews are scheduled to be conducted in July to select the team.

Baseball/Softballs Fields – Proposals have been submitted and are under review.

Dormitory – An architect has been selected to design the building.

Louise Herrington Patriot Center – Building to open soon. The 127,500 square-foot complex includes classrooms, faculty offices, indoor jogging/walking track, exercise equipment, free weight area, gymnasium/convocation area with volleyball and basketball courts, racquetball courts and an outdoor pool.

Parking Lot – A contract has been awarded to C Construction to construct a 245-space parking lot in front of the Cowan Center (facing Varsity Drive). The parking lot will include sidewalks, lighting, landscaping and irrigation. Work expected to be completed in September.

Premier Soccer Field – Request for Proposals are being prepared.

Longview University Center monument signs – Proposals were opened in June. A contract is expected to be awarded in mid-July. There will be two 46-foot lighted concrete and masonry monument signs, one on each side of the entrance to the Longview campus.

Palestine Signs – Request for proposals are being prepared.



Contact person: Emily Battle, (903) 565-5604