Construction
Projects

Construction
site of Engineering, Sciences and Technology Building
Baseball/softballs
fields - Phase I – Nearing
completion. Phase I includes the earthwork, drainage, grading,
retaining walls, irrigation and sod.
Baseball/softball
fields - Phase II – Request for Proposals were
issued with proposals submitted on Sept. 9. Scope of work
in this phase is the concession building shell and the
grandstands for both fields.
Dirt
berms, landscaping and sidewalks along Campus Drive – Project
nearing completion. Additional irrigation and landscaping
being installed.
Dormitory – Construction
estimated to begin in October 2004. Dormitory will be five
stories with 268 beds. Expected to open in fall 2006.
Engineering,
Sciences and Technology Building – Project
underway. Building expected to be ready for usage by fall
2005. Library parking lot expansion – Design completed.
Performance soccer field – Project
completed.
University
Center Room 118 Renovation – Room is being renovated to begin serving lunch
catered by Traditions. Renovations are expected to be completed in September
2004.
Other Projects – Parking Lot 6 expansion, HPE building renovations
and addition of University Center grill completed.

Contact
person: Emily
Battle, (903) 565-5604

|