Construction
Projects
Baseball/softballs fields - Phase I – Completed. Phase I includes the earthwork, drainage, grading, retaining walls, irrigation and sod.
Baseball/softball fields - Phase II – Nearing Completion. Scope of Work includes the grandstands for both fields and some lighting.
Baseball/softball fields - Phase III – Design of project to be completed in June 2005. Scope of Work to include entrance to the fields, pedestrian walkways and the field house/concession building.
Engineering, Sciences and Technology Building – Project underway. Building expected to be ready for usage by fall 2005.
Health Clinic – A contract has been awarded to RPR Construction. Work is underway. Location is on the corner of Patriot Drive and Spur 248.
Library parking lot expansion – Design completed.
Residence Hall – Project underway. Residence hall will be five stories with 268 beds. Expected to open in fall 2006.
University Center Renovation – Carter Burgess Architects is preparing the schematic design for the renovation of University Center.
Patriot Village Overflow Parking Lot – Currently under design.

Contact
person: Lisa Buchanan, (903) 565-5769

|